Miller Elementary

Phasing Plan
What to expect in the coming years...
2022
-
School Corporation Wide Exterior LED Lighting Upgrades
2023
-
Building new Kitchen/Cafeteria while repurposing old Cafeteria into LGI/Multipurpose Room.
-
Playgrounds: ADA Compliant Surfacing, New Equipment (as needed), Sensory Equipment (as needed)
-
Exterior Site Updates: Pavement, Sidewalks, Curbs
-
Additional Safety: Replace Fencing/Gates/Railings, 3M Security Film at High Traffic Locations, Bollards near Entry Points, Card Access for Convenient/Secure Entry
2024
-
HVAC and Finishes (1/2 of building)
-
Windows
-
Interior LED upgrades
2025
-
HVAC and Finishes (remaining building)
-
Interior LED upgrades